Lot 516 Tuen Mun Basement Construction


Client:            L'Avenue International Holdings Limited
Completion Date: Q3 2020
Location:        Lot No. 516, Tsing Ha Lane Tuen Mun, Hong Kong

This project involved the construction of a two-storey basement structure in advance of the superstructure construction.

The site coverage was 98m (length) by 80m (width) and the profile was complicated due to the 15m level difference and the need to build over an open culvert that is in use. Special care was taken during the construction of the cantilever structure to ensure uninterrupted functioning of the existing open culvert. Even with these challenges, the project was completed in just 7.5 months.

1 - Tuen Mun Basement Construction - Site Coverage

2 - Tuen Mun Basement Construction - View of Site

3 - Tuen Mun Basement Construction - View of Site

4 - Tuen Mun Basement Construction - View of Site

5 - Tuen Mun Basement Construction - Existing Box Culvert on Site

6 - Tuen Mun Basement Construction - Completed Basement Structure up to Ground Floor